05.05.2021

Approval of the incremental capacity projects in accordance with Regulation (EU) 2017/459 (NC CAM)

Gas Transmission Operator GAZ-SYSTEM S.A. informs that together  with the decisions of the President of the Energy Regulatory Office  issued on 29 April 2021, the administrative proceedings for the approval of three incremental capacity projects conducted in accordance with Art. 28 sec. 1 and 2 and article. 8 sec. 9, art. 25 sec. 1 of Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and repealing Regulation (EU) No 984/2013 have been completed.

  • Incremental capacity project on the border between Poland (E-Gas Transmission System) and Germany (Trading Hub Europe) at the GCP GAZ-SYSTEM/ONTRAS interconnection point was approved on April 29, 2021 by the decision of the President of the Energy Regulatory Office no. DRG.WRG.748.10.2020.ABu1

Publication of documents and necessary information can be found in the Customer Zone - Market Consultation

  • Incremental capacity project on the border between Poland and the Czech Republic was approved on April 29, 2021 by the decision of the President of the Energy Regulatory Office no. DRG.WRG.748.9.2020.ABu1

Publication of documents and necessary information can be found in the Customer Zone - Market Consultation

  • Incremental capacity project on the border between Poland (TGPS) and Germany (Trading Hub Europe)  was approved on April 29, 2021 by the decision of the President of the Energy Regulatory Office no. DRG.WRG.748.8.2020.ABu1

Publication of documents and necessary information can be found in the Customer Zone - Market Consultation


GAZ-SYSTEM is a strategic company for the Polish economy. It is responsible for the transmission of natural gas, manages the most important gas pipelines in Poland and owns the President Lech Kaczyński LNG Terminal in Świnoujście.

As part of the 2015-2025 investment programme, GAZ-SYSTEM is constructing over 2000 km of new gas pipelines in the western, southern and eastern parts of Poland. Over a dozen new gas pipelines are under construction within the North-South Gas Corridor and the compressor station in Kędzierzyn Koźle, as well as interconnections with Lithuania and Slovakia. Onshore gas pipelines are planned to connect the planned FSRU floating terminal in the Gulf of Gdansk with the national transmission system. The LNG Terminal in Świnoujście is also being extended, as a result of which the regasification capacity of this facility will be increased by more than a half.

The company is also implementing one of the most important infrastructural projects in the country - the Baltic Pipe project which consists in the construction of a two-way offshore gas pipeline connecting Poland and Denmark, expansion of the local transmission network and three gas compressor stations.

 