GAZ-SYSTEM has completed an important stage of the reconstruction of the Goleniów–Police gas pipeline

In November this year, the company completed the first stage of this investment. It involved the execution of HDD directional drill in the Intersect technology beneath the Odra River.

“The economy of the West Pomeranian Voivodeship will benefit from the reconstruction of the Goleniów–Police gas pipeline. Additionally, by dint of exploiting this method of carrying out the investment, transport between Świnoujście and Szczecin using inland vessels with a larger tonnage will be feasible” – said Krzysztof Jackowski, Vice-President of GAZ-SYSTEM.

The Goleniów–Police gas pipeline represents one of the most crucial elements of the gas transmission network in Western Pomerania. It supplies gas, among others, to the City of Szczecin and chemical plants in Police. This investment was broken down into two stages.

The first stage encompasses crossing through Roztoka Odrzańska by the underground passage method and disassembling two lines of the old DN500 and DN400 gas pipeline. During these works executed in Roztoka, the first in Poland, a 1814m long HDD-directional drilling was made. The works using this method consisted of simultaneous drilling of a pilot borehole from opposite river banks in two directions. The drilling, along with the sinking of the gas pipeline, was being performed from September to November.

The second stage of the investment will commence next year. As per the assumptions adopted, a new, 8 km long gas pipeline will be installed in the communes of Police and Stepnica. Trenchless technology will also be used on this occasion. In total, four drillings, ranging from 700 m to 2,000 m in length, will be executed. This stage is scheduled to be completed in 2023.

The environmental aspect of this undertaking is also of high importance. The scope of works involves the disassembly of approx. 4 km of the old gas pipeline running through the area across the Olszanka Reserve. Dismantling the pipe abolishes the obligation to maintain a controlled zone for the gas pipeline, therefore no need to monitor and interfere with nature there will arise. What will be the outcome is a greater development of fauna and flora and free migration of animals within the reserve.

GAZ-SYSTEM plays a strategic role in the Polish economy. We are responsible for natural gas transmission and operate the most important gas pipelines in Poland. As part of the 2015-2025 investment programme, GAZ-SYSTEM plans to build over 2000 km of new gas pipelines in western, southern and eastern parts of Poland. Further development of the national transmission network, including the construction of new gas pipelines making part of the North-South Gas Corridor, as well as the construction of interconnections with the neighbouring countries, will strengthen Poland’s energy security and make an important contribution to the development of the European transmission system.

The Company is implementing one of the most important infrastructural projects in Poland – the Baltic Pipe project, which consists in the construction of a bidirectional offshore gas pipeline connecting Poland and Denmark and the expansion of the local transmission network.

GAZ-SYSTEM also owns Polskie LNG, the operator of the President Lech Kaczyński's LNG Terminal in Świnoujście.

 