Szczecin-Lwówek gas pipeline

Description of the investment

The project consists of the development of the gas pipeline Szczecin-Lwówek, located within the territory of zachodniopomorskie, wielkopolskie and lubuskie voivodships.


Read more about the project at Investment completed section.


Investment costs 

  • estimated investment value: 556.71 MM PLN
  • co-financing from OPI&E: 164.78 MM PLN

 

Press release

17.09.2015 Completion of the Szczecin-Lwówek gas pipeline finalizes the investment program of GAZ-SYSTEM S.A.

1.08.2012 - More GAZ-SYSTEM S.A. gas pipelines with approved EU co-funding

2.07.2012 - GAZ-SYSTEM S.A. selected the contractor of the Szczecin-Lwówek gas pipeline

14.06. 2012 - GAZ-SYSTEM S.A. signed a partial agreement for the supply of steel pipes for the Szczecin-Lwówek route gas pipeline

27.03.2012 - GAZ-SYSTEM S.A. has signed an investor's supervision contract over the construction of the Szczecin-Lwówek gas pipeline

27.03. 2012 - Decision regarding the building permit of the gas pipeline on the Szczecin-Lwówek route, the Gorzów Wielkopolski-Lwówek section

28.02.2012 - Decision on the building permit for the gas pipeline on the Szczecin-Lwówek route, on the Gorzów Wielkopolski-Lwówek section

 

Project co-financed by the European Union from the European Regional Development Found.