Rembelszczyzna – Gustorzyn gas pipeline

Description of the investment

The aim of the project is construction of the Rembelszczyzna - Gustorzyn gas pipeline, 176 km in length, located within the territory of mazowieckie and kujawsko-pomorskie voivodships.

At the end of April 2015, the Construction Supervision Inspector of the Mazowieckie Province in Warsaw issued the occupancy permit for the stage of the new Rembelszczyzna-Gustorzyn gas pipeline placed in the Mazowieckie Province.
Similar administrative permits were issued in March 2015 for the stage of the project placed in the Kujawsko-Pomorskie Province.

Read more about the project at Our Investments section.


Investment costs

  • estimated value of the investment: 584.78 MM PLN
  • EU support from the OPI&E: 174.12 MM PLN




 

Project co-financed by the European Union from the European Regional Development Found.