Gustorzyn-Odolanów pipeline

Description of the investment

The aim of the project was construction of the Gustorzyn–Odolanów gas pipeline, 168 km in lenght, located within the territory of the wielkopolskie and kujawsko-pomorskie voivodships.

The starting point of the gas pipeline is located in the Odolanów network connection point whereas the end point is found in the Gustorzyn network connection point.

July 2014, the Wielkopolski Voivode and Kujawsko-Pomorski Voivode issued decisions on the use permit for Stage 1 of the new Gustorzyn-Odolanów gas pipeline. In November 2014, the building of gas pipeline was finished and the exploitation permission was given.

Read more about the project at Investments completed section.


Investment costs

  • estimated value of investment: 511.38 MM PLN
  • co-financing from OPI&E: 194.11 MM PLN

 

Press release

27.11.2014 - The construction of the Gustorzyn-Odolanów gas pipeline was completed - another pipeline received the operating permit.

22.07.2014 - Construction of Stage 1 of Gustorzyn-Odolanów gas pipeline completed

1.08.2012 - More GAZ-SYSTEM S.A. gas pipelines with approved EU co-funding

27.03.2012 - Decision on the building permit for the gas pipeline on the Gustorzyn-Turek section of the Gustorzyn-Odolanów route

13.01.2012 - GAZ-SYSTEM S.A. signed an agreement for the construction of the Gustorzyn-Odolanów gas pipeline

 

Project co-financed by the European Union from the Operational Programme Infrastructure and Environment.