Transmission capacity
Below is information on the principles of determining available capacity in given entry and exit points from the transmission system.
We hereby inform that all data about the available transmission capacity included in the files presented below has been given for information only and it does not constitute an offer within the meaning of Article 66 and subsequent articles of the Civil Code.
In order to acquire rights to transmission capacity it is necessary to file an application for the provision of transmission services to the Gas Transmission Operator GAZ-SYSTEM S.A. The application form may be downloaded from our website » more
We also inform that the available transmission capacity at the entry/exit points depends jointly on the two following elements which must be fulfilled simultaneously:
- available capacity of the measurement system at the entry/exit point, and
- available capacity of the network (gas pipelines)
Current Data
Available capacity at entry points
Technical capacity of the station at entry points
Available capacity at exit points
Technical capacity of station at exit points
Transmission capacity level:
- Transmission capacity available, usage - below 85%,
- Usage of transmission capacity - between 85% and 98%,
- Transmission capacity not available, usage over 98%.
Historical Data:
Indexes of average annual utilisation of capacity in 2007 at entry points.
Indexes of average annual utilisation of capacity in 2007 at exit points.
Indexes of average annual utilisation of capacity in 2008 at entry points.
Indexes of average annual utilisation of capacity in 2008 at exit points.
Transmission utilisation:
- Utilisation up to 20%,
- Utilisation above 20%, up to 40%,
- Utilisation above 40%, up to 60%,
- Utilisation above 60%, up to 80%,
- Utilisation above 80%.