17.05.2019

Goleniów-Lwówek gas pipeline – a location decision has been issued

On 15 May 2019, the Governor of the Greater Poland Province issued a location decision for the project entitled “Construction of the Goleniów-Lwówek DN1000 Gas Pipeline”. This is the first location decision for a project under the Baltic Pipe programme.

The construction of the Goleniów-Lwówek gas pipeline is one of the five projects implemented as part of the Baltic Pipe project in Poland. The gas pipeline will be approximately 191 km long, its nominal diameter will be 1000 mm and its operating pressure will be 8.4 MPa.

It will be constructed along the existing Szczecin-Lwówek gas pipeline. The pipeline will be constructed in three provinces: West Pomerania Province, Lubusz Province and Greater Poland Province. It will pass through 15 communes: Goleniów, Maszewo, Stargard, Dolice, Przelewice, Pełczyce, Strzelce Krajeńskie, Zwierzyn, Santok, Deszczno, Skwierzyna, Przytoczna, Pszczew, Międzychód and Lwówek.

The planned gas pipeline will ultimately be constructed in two sections:

  • section 1: from Goleniów to Ciecierzyce, with a length of approximately 122 km;
  • section 2: from Ciecierzyce to Lwówek, with a length of approximately 69 km.

The project is to enable more gas to be received from the Baltic Pipe offshore gas pipeline and from the LNG Terminal in Świnoujście. Its implementation will also be an important element of the North-South Gas Corridor.

***

Baltic Pipe is a project implemented in close cooperation between GAZ-SYSTEM, a Polish gas transmission operator, and Energinet, a Danish transmission system operator for gas and electricity. It is meant as a new route for the supply of natural gas from Norway to the Danish and Polish markets and also to end users in neighbouring countries. Once implemented, the project will enhance energy security in Poland and in the entire CEE region and increase the competitiveness of the Polish gas market.Baltic Pipe consists of 5 components:

  • a gas pipeline on the North Sea seabed (an offshore gas pipeline between the Norwegian and Danish gas transmission systems);
  • the extension of the Danish transmission system (the extension of the existing transmission system in Denmark);
  • a gas compressor station in Denmark (a gas compressor station located in the eastern part of Zealand);
  • a gas pipeline on the Baltic Sea seabed (an offshore gas pipeline between the Danish and Polish gas transmission systems);
  • the extension of the Polish transmission system (the extension of the existing transmission system in Poland).


The projects planned in Poland, apart from the construction of the Goleniów-Lwówek gas pipeline, include:

  • the construction of the gas pipeline connecting the offshore gas pipeline to the national transmission system;
  • the extension of the Goleniów Gas Compressor Station;
  • the construction of the Gustorzyn Gas Compressor Station;
  • the extension of the Odolanów Gas Compressor Station.


More information about the Baltic Pipe project

 

GAZ-SYSTEM plays a strategic role in the Polish economy. We are responsible for natural gas transmission and operate the most important gas pipelines in Poland. As part of the 2015-2025 investment programme, GAZ-SYSTEM plans to build over 2000 km of new gas pipelines in western, southern and eastern parts of Poland. Further development of the national transmission network, including the construction of new gas pipelines making part of the North-South Gas Corridor, as well as the construction of interconnections with the neighbouring countries, will strengthen Poland’s energy security and make an important contribution to the development of the European transmission system.

The Company is implementing one of the most important infrastructural projects in Poland – the Baltic Pipe project, which consists in the construction of a bidirectional offshore gas pipeline connecting Poland and Denmark and the expansion of the local transmission network.

GAZ-SYSTEM also owns Polskie LNG, the operator of the President Lech Kaczyński's LNG Terminal in Świnoujście.

 


Copyright © 2016 Gas Transmission Operator GAZ-SYSTEM S.A. All rights reserved.