Tworóg - Kędzierzyn Koźle gas pipeline

Description of the investment

The purpose of the project is to construct a high-pressure gas pipeline at the section from Tworóg to Kędzierzyn-Koźle. The pipeline is to be around 46 km long. Its diameter will be 1000 mm.

The gas pipeline will be located in:
• the Śląskie Voivodeship, in the municipalities of Tworóg, Wielowieś, Toszek, Rudziniec,
• the Opolskie Voivodeship, in the municipality of Kędzierzyn-Koźle.
The gas pipeline will mostly run along the existing high-pressure gas pipeline.
Planned project duration: 2017 – 2018.

The project will be carried out by the Consortium of MGGP S.A. in Tarnów and MGGP PROJEKT Sp. z o.o. in Kraków. which was selected during the public procurement procedure.


Advantages of the investment

The project will improve the security and reliability of natural gas transmission in the Opolskie and Śląskie Voivodeships. It will also increase transmission capacity and the diversification of natural gas sources in Poland. In addition, the Tworóg – Kędzierzyn-Koźle gas pipeline will be an element of the North-South Gas Corridor, which connects the LNG terminal in Świnoujście with the planned LNG terminal in Croatia.

An important benefit for local communities will be a real estate tax of 2% of the value of a gas pipeline section located in a given municipality which GAS-SYSTEM S.A. will pay every year.

Cost of the investment

Estimated investment value: around 311 MM PLN.

Environmental permit issued for gas pipeline Tworóg-Kędzierzyn Koźle

On 16 October 2015, the Regional Director for Environmental Protection in Katowice issued an environmental permit for the project titled “The construction of DN 1000 MOP 8.4 MPa gas pipeline, section Zdzieszowice-Kędzierzyn and Tworóg-Kędzierzyn” which makes part of the development of the gas pipeline Tworóg-Kędzierzyn-Zdzieszowice-Wrocław together with the necessary supporting infrastructure required for its operation within the territory of Śląskie, Opolskie and Dolnośląskie Voivodeships (decision ref. no. WOOŚ.4231.2.2015.JW.13).

Project of Common Interest

In October 2013, the European Commission granted the status of the Project of Common Interest to the project. More information about the meaning of PCI status for the development of the gas transmission infrastructure is presented here and in the brochure on PCI projects. Subject to meeting additional requirments, the project might also be eligible for the EU funding under the Connecting Europe Facility (CEF), which will apply under the European Union financial perspective 2014-2020.

GAZ-SYSTEM S.A. carries out the Tworóg - Kędzierzyn Koźle project without prejudice to rights of all stakeholders. Please, submit your notes, comments and questions concerning the Tworóg - Kędzierzyn Koźle project, which is the Project of Common Interest, via this form.

Tworóg-Kędzierzyn Koźle gas pipeline is planned to co-financing from the Operational Programme Infrastructure and Environment.

Press release

27.01.2015 Consultations regarding the list of Projects of Common Interest

21.02.2014 Projects of Common Interest (PCI) conducted by GAZ-SYSTEM S.A.: publication of an information brochure

15.10.2013 Selected infrastructure projects of GAZ-SYSTEM S.A. were awarded the status of projects of common interest (PCI)

 

 


Newsletter
Copyright © 2016 Gas Transmission Operator GAZ-SYSTEM S.A. All rights reserved.