Świnoujście-Szczecin gas pipeline

Description of the investment

The aim of the project was the construction of the Świnoujście - Szczecin gas pipeline which is 800 mm in diameter and 80 km in length. The gas pipeline will cross five communes of the zachodniopomorskie voivodship: Świnoujście, Międzyzdroje, Wolin, Stępnica and Goleniów, connecting the LNG Terminal in Świnoujście with the Polish transmission system in the Goleniów region.

The investment is connected with the arising liquefied natural gas (LNG) regasification terminal in Świnoujście, and also constitutes an element of the development of the cross-border transmission infrastructure in the Baltic Sea region (Baltic Interconnection).

On June 2014, The Governor of the Zachodniopomorskie Voivodeship issued a decision on granting a permit to use the high-pressure transmission gas pipeline at the section from Świnoujście to Szczecin.  

 

Route of the gas pileline

 

Benefits

  • significant element in the development of cross-border transmission infrastructure in the Baltic Sea region,
  • efficient gas transmission to customers in Poland and in neighbouring countries, including to markets in Denmark and Sweden, after the planned connection of the Polish transmission system with the Danish system via the Baltic Pipe gas pipeline,
  • improvement of gas transmission security in the northwestern part of the country,
  • increasing the energy security of Poland and of other countries in the region.

Communes which have a gas pipeline running through their territory will obtain additional funding in the form of a property tax paid annually by the investor in the amount of 2% of the investment value located in the given Commune. This will be a sum that will regularly contribute to the Commune's budget and that can be allocated for the needs of the residents and local communities.

 

Investment costs

  • estimated investment value: 85.76 MM EUR
  • co-financing from EEPR: 50.00 MM EUR

Read more about the co-financing the project from European Energy Programme for Recovery.



Information about compensations

  • Zachodniopomorskie Voivodship Office
    phone: + 48 91 4303 671

 


Press release

23.06.2014 - The newly constructed Świnoujście-Szczecin gas pipeline obtained a use permit

8.02.2012 - GAZ-SYSTEM S.A. is buying pipes for the construction of strategic gas pipelines

29.12.2010 - Location Decision for the Świnoujście - Szczecin gas pipeline

 

 

 

   