Urgent Market Messages

Publication according to Article 4 (1) of REMIT- Urgent Market Message by the Regulation of the European Parliament and the Council (EU) No 1227/2011 on wholesale energy market integrity and transparency
17-53ZPL0000760162T-00006_002 Unplanned event in the GAZ-SYSTEM S.A. transmission system
Event status Inactive
Type of unavailability Unplanned
Type of event Transmission system unavailability
Publication 2017-02-28T13:38:38+01:00
Start 2017-02-28T08:30:00+01:00
End 2017-02-28T13:10:00+01:00
Unavailable capacity 200700 kWh/h
Available capacity 0 kWh/h
Technical capacity 200700 kWh/h
Reason of the unavailability On Interoperating  System Operator’s  side. Look at the "Comment" filed.
Comment Shutdown the station Szczecin Warszewo at the request of PSG due to the leak on PSG gas grid
Balancing zone 21Y000000000087V
Affected asset or unit Szczecin Warszewo, exit point
Affected asset EIC Code 53ZPL0000760162T
Market Participant GAZ-SYSTEM S.A.
Market Participant Code A0001079H.PL
Related messages 17-53ZPL0000760162T-00006_001