22.05.2018

GAZ-SYSTEM commences construction works on the Tworóg – Tworzeń gas pipeline

On May 8, 2018, GAZ-SYSTEM concluded a contract for construction of the Tworóg - Tworzeń pipeline with the consortium, consisting of: PORR S.A. and Denys NV.

The Tworóg – Tworzeń gas pipeline is going to be built in Śląskie Province and will constitute an element of the eastern line of the North-South Corridor. Its diameter is 1000 mm, pressure - 8,4 MPa, and the length exceeds 55 km.
The route of the gas pipeline is going to cross through the following communes: Tworóg, Tarnowskie Góry, Miasteczko Śląskie, Ożarowice, Mierzęcice, Siewierz and Dąbrowa Górnicza.

Implementation of this project will contribute to an increase of transmission capacities and give an added value to the areas provided for new investments within the region, yet in terms of national advantages, this undertaking will enhance security and diversify deliveries of natural gas to Poland. On the other hand, a crucial benefit for the local community is a yearly property tax of 2% off the value of gas infrastructure located within the premises of the commune, to be paid by the company. 

In October 2013, the European Commission granted the investment the PCI status. The construction of the gas pipeline is financed with the European Regional Development Fund within the Operational Program Infrastructure and Environment 2014-2020.

The investment supervision of this venture is going to be held by ECMG GmbH, whilst TRACTEBEL ENGINEERING S.A., a contractor of design plans and documentation, will be in charge of the author’s control. 

The project is a part of investment accompanying undertakings related to the regasification terminal of liquid petroleum gas, based in Świnoujście, and is subject to, so called, special purpose gas act.

The construction works are planned to be closed in 2020.

 

Kliknij, aby powiększyć

GAZ-SYSTEM plays a strategic role in the Polish economy. We are responsible for natural gas transmission and operate the most important gas pipelines in Poland. As part of the 2015-2025 investment programme, GAZ-SYSTEM plans to build over 2000 km of new gas pipelines in western, southern and eastern parts of Poland. Further development of the national transmission network, including the construction of new gas pipelines making part of the North-South Gas Corridor, as well as the construction of interconnections with the neighbouring countries, will strengthen Poland’s energy security and make an important contribution to the development of the European transmission system.

The Company is implementing one of the most important infrastructural projects in Poland – the Baltic Pipe project, which consists in the construction of a bidirectional offshore gas pipeline connecting Poland and Denmark and the expansion of the local transmission network.

GAZ-SYSTEM also owns Polskie LNG, the operator of the President Lech Kaczyński's LNG Terminal in Świnoujście.

 